The installation of new water mains and new connection to all T’s and V’s is now complete.

We have changed our electrical supplier to achieve superior tariffs for Pools and street lighting. This should show a considerable saving on our costs.

We are currently removing the large metal plate that acts as a cover for the Manhole between 16 and 76 and replacing with proper manhole covers. We are also changing manhole covers to pathways where needed.

We are moving a few water meters to more accessible positions for the owners to turn off the water when they leave and also make reading the meters easier.

The heating to the Pools has been turned off for the Summer months.

Brian

3rd May 2016

Overhead lighting has been installed for the Pool by Los Amigos for safety purposes as the internal Pool Lights are failing on a regular basis. This will save the costs of constantly repairing the lighting system and make any maintenance to the exterior lighting system easier to maintain. The other pool will have overhead lighting in the near future.

Pruning Palm Trees.

Approx 8 trees left to prune to complete this years pruning.

Picon

Several loads of Picon have been spread to gardens where owners requested. Should you need Picon to your garden please contact Luis and he will place you on the List.

New Water System Ts and Vs

There are 28 apartments to have the new water system installed, twenty have now been connected. The remaining 8 properties should be connected by the end of this week.

Street Lights

We are continuing to improve the street lights ref new wiring and the LED Bulbs being installed.

We have complained to the Town Hall several times ref the Common area in the front of Playa Bastian. Full of Weeds and rubbish. Two weeks ago the Town Hall sent a representative to inspect the area. Today a large group of workers descended on the area and totally cleared the rubbish making the front of the Complex vastly improved.

 

Brian