19th June

 

The new store/internet room is proceeding .  All the walls should be built this week.  Walls then to be rendered.

Permit for recycled water has been received and we are completing more paperwork before we can make final connections.  This should prove beneficial for the Gardens.

Brian

8th June

The promenade gate has been vandalised several times and the cost of repairs to the Community is becoming a problem.  Unfortunately it has been damaged again and would not lock so once more we had to call the electrician out. The gate keypad had been smashed by a rock, we have had to replace the keypad and Miguel has also made metal cages to protect them from similar damage.

The current camera arrangement has proved less than successful in deterring or catching any vandals or thieves. We are currently looking to upgrade the cameras within Zone D and adding an additional camera overlooking the gate area.

We needed to replace the waste bins around the Zone, to buy new ones for the road and swimming pools would have cost the community €95 per bin.  Miguel has made seven new bins at €25 per bin .  A really top class job.  Another of Miguel’s many skills.

The extension to the maintenance teams store has started.  Foundations being dug and concreted as we speak.  This store also includes secure locked premises for our equipment, plus the internet room, now that this has been passed at the recent EGM.

Brian