23rd July 2015

We are installing a Gate at the top of the Steps of Piscina 2 as we regard this as a safety issue.

We are also fitting a device between 106B and 107 to prevent vehicles parking there as several times the Kerb stones have been damaged by Vehicles.

Luis is on holiday over August. Roberta will be standing in for him.

Brian

19th July 2015

We have been installing two new runs of water main from 90 – 94 and 99a to 100b. We have been replacing the pipes to the house meters from the main pipe run

Maintenance Team Holidays :

Todao is on holiday this month
Javier has August for his month.
Miguel will take 2 weeks in September and make the remainder of his holiday taking thursdays off.

The internet as a whole has been running well with no major problems. Any issues we do have are mainly related to individual properties rather than the system.

The TV project is advancing well thanks to Hedley, Ken and Julian. We have all the equipment installed and have got eight British and German digital channels working. We have also upgraded the terrestrial TV system coming through the normal TV aerial so that there will be all the local Spanish and Canarian stations as well. We still have to carry out further testing to iron out a few minor issues, but we are almost there!

Brian