1de diciembre

We are continuing to install new cable for street lighting.

The wall to the centre road is being refurbished by Todao and is looking good.

As many of the bases to the street lights are corroding making changing bulbs and globes on a ladder dangerous we are currently trialing new lower lights which also eliminate light pollution.

Existing walkway manhole covers being improved and repaired for safer walking.

The Bar refurbishment is almost complete and should reopen in the next few weeks .

An extra telephone line is being installed to assist the wi fi system to half the loading from the TV room, as we are nearing capacity for one line to the area

Brian

22nd octubre,,en,Todavía estamos tratando con la infestación en el Hibiscus,,en,El consejo de expertos es rociar cada quince días y dos días después lavar las plantas,,en,Se necesitan varios días para completar esta tarea y es, obviamente, de manera intensiva la mano de obra que no podemos seguir el ritmo de otros trabajos de jardinería,,en,La única manera de lograr una solución satisfactoria al problema es el empleo de una cuarta persona de forma temporal para llevar a cabo los trabajos requeridos en el hibisco y liberar los jardineros para su trabajo normal,,en,Donde los propietarios han solicitado que hemos eliminado del hibisco que se ven afectados por la infestación,,en,Hemos reemplazado recientemente en el cable coaxial de edad,,en,áreas en las que habían sufrido la degradación debido a la exposición al sol,,en,Los policías de dormir parecen estar teniendo el efecto deseado,,en 2013

Desde que se informó sobre los problemas de alumbrado público en el boletín de otoño, lamentablemente la situación se ha deteriorado aún más.. Hemos encontrado cables adicionales que han fallado debido a daños por inmersión prolongada en agua en los macrones. ( Las tuberías subterráneas que llevan los cables.). Esto ha causado problemas con las luces en la carretera principal hasta la puerta y a lo largo de la carretera lateral detrás. 200.

El electricista junto con la ayuda de Hedley. (203) está gestionando soluciones temporales, pero estos cables también necesitarán ser reemplazados como parte de la renovación del sistema de iluminación..

Brian

19de octubre 2013

Hongo/mosca blanca

Nos hemos puesto en contacto con un experto sobre el problema actual de las Plantas.. Estamos utilizando los productos químicos correctos para el problema.. El único tratamiento adicional es lavar las plantas con manguera después de tratarlas con productos químicos., que ahora implementaremos.

Actualmente estamos reparando la cerca dañada cerca de Casa J por personas desconocidas.. Esta valla se encuentra en general en mal estado y requerirá más trabajos en un futuro próximo..

Seguimos mejorando el cable de alumbrado público y ahora hemos completado otra sección.. Este trabajo continuará mientras el problema persista..

Brian

2nd octubre,,en,Todavía estamos tratando con la infestación en el Hibiscus,,en,El consejo de expertos es rociar cada quince días y dos días después lavar las plantas,,en,Se necesitan varios días para completar esta tarea y es, obviamente, de manera intensiva la mano de obra que no podemos seguir el ritmo de otros trabajos de jardinería,,en,La única manera de lograr una solución satisfactoria al problema es el empleo de una cuarta persona de forma temporal para llevar a cabo los trabajos requeridos en el hibisco y liberar los jardineros para su trabajo normal,,en,Donde los propietarios han solicitado que hemos eliminado del hibisco que se ven afectados por la infestación,,en,Hemos reemplazado recientemente en el cable coaxial de edad,,en,áreas en las que habían sufrido la degradación debido a la exposición al sol,,en,Los policías de dormir parecen estar teniendo el efecto deseado,,en 2013

Hola

Ahora hemos repintado el área de Promenade Gate., incluyendo las paredes y la puerta, después del daño del teclado. Desafortunadamente, el cierrapuertas ha sido objeto de vandalismo nuevamente y será reemplazado por un cierre más fuerte..

Estamos fumigando las plantas y arbustos nuevamente para hongos ya que la isla todavía tiene el problema de los hongos..

Ya hemos hablado con Canal Gestión, la nueva empresa de agua, y con suerte mejoró la presión del agua en los jardines.. Agradecemos los mensajes positivos que hemos recibido sobre la forma en que crecen las plantas con el nuevo sistema..

Todo el equipo ya está de vuelta al trabajo después de las vacaciones de verano..

Brian

 

11th September 2013

Virtually all suspect cabling for the lights has been replaced. What has become apparent during this operation is that the insulating cable has broken down and has caused the problems. Additionally, it is been impossible to use the existing ducts in places. This has made it a larger project than we envisaged.

Miguel is currently on holiday and by September end the Team will have used all their holiday entitlement.

The new water company, initially insisted on installing extra filters to the system which effected our pressure. They have since agreed to remove them and we should now have improved pressure.

Brian

13de agosto 2013

Further to the last blog about the issues we have been having with the complex lights, it is becoming apparent that the oldest area of the complex has cabling past its sell by date. The replacement of Cables is proving more extensive than we envisaged at the start. It is more the cable insulation on the outside that’s broken down rather than the cable itself.

Hedley Smith 203, has been a great help with this problem and liaises with the electrician.

Brian

5de agosto 2013

The rewiring of the Lights has now been completed in the affected areas and all complex lights are now working. This has been a difficult re-cabling project. Now the earth stakes are being installed.

For a period of 2 weeks from Tuesday 6th August, reception will have a limited opening time from 9.00am to 1.00pm.

 

Brian

26de julio 2013

Se sigue trabajando para tratar de resolver los problemas con las luces de la calle y los cables corroídos,,en,Varios de los conductos subterráneos que llevan el cableado de la luz de la calle tienen ahora colapsado totalmente,,en,Vamos a tener que cambiar la ruta de nuevos cables a través de nuevos conductos y en una o dos áreas desenterrar el camino por carretera,,en,Obviamente una estrecha vigilancia tiene que ser mantenido en el precio,,en,pero este trabajo es inevitable y formará una parte de la obra Industria eventualmente nos pida para llevar a cabo,,en,Actualmente estamos cambiando carreras de conducción de aguas jardín existente para la nueva como en muchas de las áreas de los tubos están perforados y romper,,en,También estamos experimentando actualmente problemas con las luces de la calle,,en. Several of the underground ducts that carry the street light cabling have now totally collapsed. We are having to re-route new cables through new ducts and in one or two areas dig up the road way. Obviously a close watch has to be kept on cost, but this work is unavoidable and will form a part of the work Industria will eventually ask us to carry out.

 

Brian

 

18de julio 2013

We are currently changing runs of existing garden water pipe for new as in many of the areas the pipes are perforated and breaking down.

We are also currently experiencing problems with the street lights. Los cables son ahora de más de treinta años de edad y que están sustituyendo a las zonas de resolver el problema y la inserción de nuevas sondas de tierra de cada cinco Poste de la lámpara,,en,El ejercicio está tomando mucho más tiempo de lo que esperábamos,,en,como en lugares acceder tapas de registro se han concretado una y oculto a la vista,,en,Debido a un error administrativo,,en,las cifras citadas en el blog anterior en relación con el ahorro de agua son incorrectos,,en,Por favor, acepte mis disculpas por este,,en,Las cifras correctas son como a continuación,,en,euro,,en,El ahorro total de los períodos mencionados son,,en,Debido al trabajo stirling llevada a cabo por el equipo de mantenimiento de la renovación de tuberías de agua de red y tuberías que pasan a metros de la casa,,en,la factura total de agua durante los primeros seis meses de este año es de 17.600 €,,en,Los primeros seis meses de,,en,€ 25.400,,en. The exercise is taking considerably longer than we hoped for, as in places access manhole covers have been concreted over and hidden from view.

Brian

 

12de julio 2013

Due to an administrative error, the figures quoted in the previous blog regarding water savings are incorrect. Please accept my apologies for this.

The correct figures are as below

2011 a 2012 – 65,473 euro

2012 a 2013 – 33,822 euro

The total savings for the periods mentioned are 31,651 euro.

Brian