8th April 2016

The new domestic mains water pipes and new supplies to all the Ts and Vs are within 2 or 3 weeks of completion.

Several loads of Picon are being delivered and spread on to gardens where owners have requested it. Just a reminder, if you do require more Picon at any time, Luis keeps the List and you can have your name added to this list then when we can fill a load we order more.

The Palm Trees are currently being pruned.

The upgrade to the street lighting is continuing.

The swimming pool internal lights continue to cause problems. We have decided to install overhead lighting to the Pool areas to make maintenance more accessible and keep costs to a minimum.

Brian

6th March 2016

I have just been informed of the sad passing of Clive Sears, Bungalow 36, in January. Myself and the Board would like to express our sincere condolences to Irene and family at this time.

Brian

1st March 2016

Hi

Co ax cable – One block Nos 50 to 54 had not had the Co Ax facility for TV or Wi Fi. Miguel and the Team have now installed the cable and all the above properties will have access.

Pruning of Palm Trees should start within the next 7 days.

We have started replacing water pipes i.e. domestic supply to the Ts and Vs.

Brian

19th February 2016

The agenda for the AGM on 12th March 2016 which has recently been posted out, is also now available on the website

We have started laying Picon on the Gardens that have requested Picon top up.

We are soon to start replacement of water pipes to the Ts and Vs as the next phase of water pipe renewal.

Brian

12th February 2016

All the Sunbeds at the swimming pool by the Ts and Vs have now had new covers fitted. The sunbed covers by Los Amigos pool will be fitted next.

We are currently fitting a new electrical supply from a meter behind Los Amigos, running to the new Tv and wifi room. We will then remove the provisional supply we are currently using. This will give the system more stability.

Brian

20th December 2015

The pruning is continuing and the area adjacent to the Coronas Hotel is almost complete.

An area to the rear of 16, 17 and 18 has had 5 meter of new pipework and metal grills fitted to alleviate the flooding issues when we have torrential rain.

I would also like to take this opportunity to wish everyone a very Merry Christmas, and a Happy new Year!

Brian