29th January 2015

Deux charges de Picon sont maintenant utilisés sur les jardins si nécessaire,,en,la taille Palm Tree progresse maintenant et est presque 1/3 terminé,,en,Les conteneurs gratuits que nous avons apprécié du Cabildo pour la collecte des boutures Palm arbres ne sont plus disponibles et à l'avenir nous allons payer pour les conteneurs privé,,en.

Palm Tree pruning is now progressing and is almost 1/3rd completed. The free containers we enjoyed from the Cabildo for collecting Palm Tree cuttings are no longer available and in future we will be paying for the containers privately.

Brian

13th January 2015

Les portes de la salle Gardeners ont finalement expiré et ont été remplacés par une paire de portes en aluminium,,en,nouveaux feux sont fournis et installés autour de la piscine du milieu, car cela est avéré besoin d'un éclairage supplémentaire et à tout moment les lumières de la piscine ne fonctionnaient pas,,en,Picon a été livré et est actuellement étalée sur les jardins,,en,Alexis a prévu dans la taille Palm Tree et commencera dès que possible,,en,Fungus / mouche blanche est actuellement sous contrôle, mais nous resterons vigilants en cas de nouvelle infestation,,en,Dans les prochaines semaines, nous allons continuer avec le remplacement du câble de l'éclairage public,,en.

2 new lights are being supplied and fitted around the middle pool as this has proved to need extra lighting and at any time the Pool lights were not working.

Picon has been delivered and is currently being spread on the gardens.

Alexis has planned in the Palm Tree pruning and will commence asap.

The Fungus/white fly is currently under control but we will remain vigilant in case of further infestation.

In the next few weeks we will be continuing with the street light cable replacement.

Brian

10th December 2014

The last container has been delivered to remove trees lost in the recent bad weather. By next week we should return to normal.

We are continuing to replace old street light cables with all the problems of underground ducts becoming crushed over the years.

In the next 2 weeks we will be having more Picon delivered.

I would like to thank Ken Harvey who has helped for several days ref the lights and cable problems.

Brian

 

27th November 2014

The Pumping Station in front of the Coronas Playa Hotel was overwhelmed by approx 10″ or 250mm of rain during the recent deluge. This caused severe flooding to zone D’s drainage system and resulted in blockages and drain covers lifting off. Currently this has all been cleared up and hopefully the rain forecast for the 28.11.14 will not bring a repeat of the situation.

As previously reported, replacing old lighting cables are causing problems with cables concreted in and new runs being laid in new ducts.

Brian

 

20th November 2014

We have now continued to replace the old street light cable. On the first run we found the lighting manhole has been covered in six inches of Concrete and the cables concreted in. This unfortunately costs time and money and obviously we have to re route new cable.

Brian

13th November 2014

We are currently rewiring the swimming pool lights to both pools as the wiring is faulty. Partly through water getting into the cable.

We also intend to install 2 street lights to Pool no.2 i.e. HPB side, as this area is dark especially when the pool lights are out.

Extra Sun Bed covers have been ordered to replace worn bed covers.

I have noticed one or two plants suffering with what appears to be possible Bleach going by the smell. Please be careful should you wash your terrace with a bleach NOT to throw the water around the Plants.

Brian

 

8th November 2014

We have turned on the Heat Pumps to both Pools.

Currently 50% of the complexes Hibiscus have to be treated for the mealy bug/whitefly. Where the owners are requesting removal of the Hibiscus this is being carried out.

The three speed bumps fitted to the main road are working well.

Luis has returned from Holiday so normal service has resumed.

Hedley Smith is retuning TVs on an almost daily basis now. I trust you all appreciate his efforts.

Unfortunately we still have issues with Canal Gestian although currently the system is working okay.

 

Brian

22nd Octobre,,en,Nous en sommes toujours à l'infestation sur l'Hibiscus,,en,Le conseil d'experts est de pulvériser tous les quinze jours et deux jours plus tard, se laver les plantes hors,,en,Il faut plusieurs jours pour terminer cette tâche et est évidemment si le travail intensif que nous ne pouvons pas suivre d'autres travaux de jardinage,,en,La seule façon de parvenir à une résolution réussie au problème est d'employer une quatrième personne à titre temporaire pour effectuer les travaux requis sur l'Hibiscus et de libérer les jardiniers pour leur travail normal,,en,Lorsque les propriétaires ont demandé que nous avons supprimé Hibiscus qui sont touchés par l'infestation,,en,Nous avons récemment remplacé ancien câble coaxial,,en,les zones où ils ont subi du fait de la dégradation de l'exposition au soleil,,en,Les policiers du sommeil semblent avoir l'effet désiré,,en 2014

We are still dealing with the infestation on the Hibiscus. The experts advise is to spray every fifteen days and two days later wash off the plants. It takes several days to complete this task and is obviously so labour intensive that we cannot keep up with other gardening work.

The only way to achieve a successful resolution to the problem is to employ a fourth person on a temporary basis to carry out the required work on the Hibiscus and to release the gardeners for their normal work.

Where owners have requested we have removed Hibiscus that are affected by the infestation.

We have recently replaced old coaxial cable in 2 areas where they had suffered degradation owing to exposure to the sun.

The sleeping policemen appear to be having the desired affect.

 

29th September 2014

Alors que Luis est en vacances,,en,Abraham sera debout à la réception,,en,Il travaillera,,en,h à,,sv,pm,,en,Du lundi au vendredi,,en,mois,,en,Il est l'espagnol avec un très bon anglais,,en,Il commencera mercredi,,en, Abraham will be standing in on reception. He will be working 9 am till 1 pm, Monday to Friday for 1 month. He is Spanish with very good English. He will be starting Wednesday 1.10.2014.

Brian